HDB Renovation Process: The Order of Works, Step by Step

The HDB renovation process follows an order, and the order exists for good reasons: dust, water, noise and measurements all affect the trade that comes next. Knowing the sequence helps you read a contractor's programme, ask better questions and spot a schedule that does not add up. This article walks through the order of works on site, with the permit gate that comes before it.
Before the first hammer swing: contract, drawings and permit
The sequence on site starts on paper. You need the rules before the design, the design before the quotes, the quotes before the contract, and the permit before permit-required works begin.
- Contract. It should state the scope, the drawings, the schedule, payment stages tied to progress, how changes are handled, and the defects period and warranties.
- Permit. Your contractor submits the renovation application to HDB electronically, with the floor plan showing the proposed work. You authorise the contractor to do this, and HDB sends you an SMS when it receives the application.
- Approval. Start permit-required works only after the permit is granted. Works that need no permit must still follow HDB's guidelines.
- Completion window. After approval, HDB expects renovation in a new flat to finish within 3 months, and within 1 month in an existing flat.
The HDB renovation process on site: order of works
A renovation with hacking and wet works commonly runs in the order below. Your contractor's programme will vary. For example, air-conditioning pipework may go in earlier.
Step | Typical work | Why it sits here | Point to check |
|---|---|---|---|
1 | Site set-up and protection | Everything that follows creates dust and debris | Floors, lifts and common areas are protected before work starts |
2 | Hacking and demolition, where permitted | The noisiest, dirtiest work comes first | Only works covered by the permit |
3 | Concealed electrical and plumbing | Pipes and conduits go in before surfaces close over them | Electrical by an EMA-licensed worker, water and sanitary work by a PUB-licensed plumber |
4 | Waterproofing and wet-area tiling | Wet areas are sealed before finishes go on | Waterproofing tested before finishes, warranty in writing |
5 | Ceiling and partition works | Sets heights and lighting positions | Heights and positions match the drawings |
6 | Carpentry made and fitted to site measurements | Needs finished walls and floors to measure against | Measurements checked on site before fabrication |
7 | Painting | Follows the trades that mark or scuff walls | Products and coats as quoted |
8 | Flooring and remaining finishes | Laid late to avoid damage | Protected until handover |
9 | Light fittings, switches, sanitary fittings, air-conditioning | Final fixings go on finished surfaces | Installed by the right licensed trade and tested |
10 | Cleaning | Removes dust before you inspect | Final clean before inspection |
Work with HDB's working hours
Noise rules shape the calendar. General works such as plastering and laying floor screed run Monday to Saturday, 9am to 6pm, and never on Sundays or public holidays. Noisy works such as demolishing walls and removing finishes are limited to Monday to Friday, 9am to 5pm, with none on weekends, public holidays or the eve of major public holidays. Since the noisiest work sits at step 2, ask your contractor to show you the hacking days on the calendar.
Five ordering mistakes that cost time
- Ordering carpentry before measuring on site. Fabrication from drawings alone risks units that do not fit.
- Ordering tiles and fittings late. The schedule then waits for stock to arrive. Confirm long-lead items such as carpentry materials, tiles, sanitary ware and lighting early.
- Starting permit-required works before the permit is granted. HDB states that unauthorised work may have to be stopped, corrected or removed.
- Starting renovation before reporting defects in the flat. Fixes become harder to attribute once works begin. See our BTO key collection checklist.
- Signing a contract without drawings. The scope is then open to interpretation.
Our BTO renovation timeline lists these mistakes alongside the nine stages, so you can tick each one off as you go.
Questions to ask your contractor about the programme
- On which days will hacking start and finish, and does that fit HDB's noisy-works hours?
- When will waterproofing be tested, and who signs it off?
- When will carpentry be measured on site, and when will it be fabricated?
- Which long-lead items, such as tiles, sanitary ware, lighting and carpentry materials, have been ordered, and when do they arrive?
- What happens to the schedule if the permit takes longer than planned?
- Which licensed trade handles each electrical, plumbing and air-conditioning step?
Inspection and handover
Near the end, walk through every room with your contractor and list anything unfinished or wrong, with photos. Test lights, points, taps, showers and drains, and check waterproofed areas for leaks. Agree a date for corrections and check them again. Make the final payment after the list is cleared, as your contract provides, and collect warranties and the documents your contractor should provide.
Renovating an HDB flat?
See the HDB homes we have designed, how we work within HDB’s rules, and what our clients say.
4.9 on Google ReviewsCaseTrust certifiedFree first consultation
Free guide from Ace’s Design
BTO Key Collection to Move-In
The nine stages from key collection to move-in, who is involved at each, and a timeline worksheet to fill in with your own dates.
Leave your details and we will email you the PDF.