Kitchen Renovation in Singapore: HDB Rules, Wet and Dry Kitchens, Order of Works

Renovation Guides
Kitchen island in walnut with two stools and a textured tile splashback

A kitchen renovation brings together more trades than any other room: hacking, plumbing, gas, electrical, tiling, carpentry and stone. Each has its own rules in an HDB flat, and each has to happen in the right order. This guide covers the rules, the layout decisions, what drives the cost and the sequence of work. For layout and design ideas, see our HDB kitchen design guide.

Start With the Layout Decision

Open or enclosed

Opening the kitchen to the living area is one of the most requested HDB changes. Removing a non-load-bearing wall needs HDB’s approval before work starts, and existing reinforced concrete must not be touched. Where a reinforced concrete partition is approved for demolition, HDB requires a Professional Engineer to supervise. Lightweight walls can only be removed up to the underside of the beam or slab above.

Wet and dry kitchen

A wet and dry kitchen splits the cooking. The wet kitchen holds the gas hob, the sink and the heavy frying, usually behind a door or glass partition. The dry kitchen sits in the open, often with an island, and holds the fridge, the oven, light prep and a breakfast counter. It is the usual way to get an open feel in a household that cooks with a wok. Glass, including fluted glass, lets light through while keeping the smoke in. Building a new partition is often simpler than removing one; see our partition wall guide.

Extending into the service yard

HDB allows the kitchen to be extended into the service yard or balcony without removing walls and without a permit, provided the services in the extended area are not tampered with and no exhaust fan is installed in the yard. Our HDB service yard design guide covers how to plan that space.

Kitchen with dark cabinetry, a timber worktop and flowers on the windowsill

Modern Luxury, at Bellewaters

HDB Rules That Shape a Kitchen Renovation

  • Gas work. All gas pipe alterations must be done by City Energy or a Licensed Gas Service Worker. Gas pipes must not be embedded in floor screed, finishes or common partition walls, or enclosed in a false ceiling. A gas riser can be boxed in only with lightweight non-combustible material and a fully ventilated removable access panel 600mm wide and full height.
  • Gas and bedrooms. Gas pipes and appliances are not allowed in a sleeping area. In a 2-room Flexi flat where the flexible space is used as a bedroom, HDB requires a full-height wall with a door between it and the kitchen. Our 2-room Flexi guide covers that layout.
  • Sinks. A sink can be repositioned, but the floor slab must not be tampered with. A sink waste pipe can be diverted within the floor finishes but not embedded in the slab, and the work must be done by a PUB Licensed Plumber.
  • Counters. A cement mortar base or counter top needs no permit, but concrete shelves are not allowed, the cement base and tiles must not exceed 50mm, and only one layer of 63mm hollow block can support the top.
  • Floors. Replacing kitchen floor tiles needs a permit, pre-packed waterproofing screed, and a waterproofing membrane turned up 150mm around the sanitary stacks for a 400mm radius. Finishes and screed must not exceed 50mm.
  • Weepholes. Some kitchens have enclosed sanitary ducts with a weephole to show leaks. HDB says these must not be sealed or blocked by carpentry.

What Drives the Cost

Kitchen renovation costs vary more than any other room because the scope varies so much. These are the items that move the total most:

  1. Hacking. Removing a wall or the old tiles adds demolition, disposal and, for a concrete wall, engineering supervision.
  2. Cabinet run and finish. Carpentry is quoted per foot run, with separate rates for base, top-hung and tall units. Our cabinet design guide explains what to compare.
  3. The worktop. Quartz, sintered stone and solid surface differ widely. See our countertop comparison.
  4. An island. An island adds carpentry, stone and often plumbing or power. Our kitchen island guide covers when it fits.
  5. Plumbing and gas changes. Moving a sink or hob adds licensed plumbing and gas work.
  6. Appliances. Built-in appliances must be chosen before the cabinets are drawn.

For how design fees fit into the total, see interior design cost in Singapore.

Kitchen cabinetry in walnut with a display niche holding a ribbed vase

Transitional Modern, at 289C Punggol Place

The Order of Works

  1. Design, measurements and appliance selection.
  2. HDB permit for hacking or tile replacement.
  3. Hacking of walls and old finishes, in HDB’s weekday noisy-work hours.
  4. Plumbing, gas and electrical rough-in by licensed workers.
  5. Waterproofing and floor and wall tiling.
  6. False ceiling and lighting.
  7. Cabinet installation, then worktop measurement and installation.
  8. Sink, hob, hood and appliance installation, then gas connection and testing.

The worktop is templated after the cabinets are in, which is why the stone goes in after the carpentry rather than with it. The full sequence for the flat is in our HDB renovation process guide.

Condo Kitchen Renovations

In a condo, HDB’s rules do not apply, but the management corporation’s by-laws do, including working hours, deposits and rules on hacking and gas. Many condo kitchens are open from the start, so the work is more often about the cabinets, the worktop and the appliances. Our condo interior design ideas and small condo interior design guides show layouts that work in Singapore condos.

Kitchen sink with a brushed steel tap below a window with vertical blinds

Modern Eclectic, at 291 Bishan

If you are planning a kitchen renovation, book a free consultation and bring your floor plan and the appliances you want to keep.

Planning a renovation?

See the homes we have designed, how we work, and what our clients say, for your type of home.

4.9 on Google ReviewsCaseTrust certifiedFree first consultation

Free guide from Ace’s Design

12 Line Items to Check in Any Renovation Quote

The 12 line items, six checks to settle before you sign, and a worksheet for setting Quote A, B and C side by side.

Leave your details and we will email you the PDF.